(Domingo 19
- Sábado 25 Mayo) Our crew is working
hard to finalize everything. Unfortunately for us and them, Frank
has rented his new house and needed to borrow Luis, our foreman, and
one other fellow for two days to finish up details there. This put
things behind here. It would not matter to us except for the fact
that Luis has promised to start another project up in Coscomatepec,
so the crew can be here only one week after this.
This week's work
has centered on reparando (repairing) the rotted ends of the decorative roof
vigas (beams) and furthest out tablas (boards) above
them at the edges of the north and west roofs. The prior
configuration of roof tiles had been constructed in such a way that
rain dripping off the roof had run back, keeping these areas almost
perpetually damp. To fix this, the guys cut off the beams back into
good wood. Wood delivered from Alejandro's mill in Coscomatepec was
trimmed to size and cut to the length needed for each beam extension.
The decorative curves and notches to match the existing beams were
crafted on the outboard ends. Then, using a very long 3/8” bit we
had brought from the US, two deep holes were bored in each viga, and
corresponding ones on the repair pieces. Rebar stubs were driven
into the holes and the new beam ends sledged into place. Then to
firm everything up further, heavy mending straps (some brought from
the US, others found at Home Depot—otherwise unavailable here in
local ferreterias), attached with lag screws.
In some cases,
channels bored by polilla ants (aerial termites) were found in
the beams, and festermicide was injected in the holes. All the wood
was treated with festermicide, and the new vigas were stained and
sealed with Thompson's WaterSeal. The other job this week was the
construction of our little bodega (small storage area), which will be
a place for tools and outdoor supplies. A short footing between the
laundry and BBQ was poured, block walls constructed, actually
incorporating part of the BBQ structure, and on saturday the roof
slab was poured.
Mauricio, our
welder. stopped by to measure and get Dan's ideas for designing the
doors for our bodega being built between the laundry and outdoor
BBQ/fireplace. They will be similar to our protective door gates,
but covered with heavy gauge sheetmetal. We bought our washer and
dryer from Home Depot, to be delivered next week thursday, and picked
up lumber for shelving jobs Dan plans once the crew is gone. This
week we had Home Depot deliver two unfinished cabinets that will be
incorporated into a seating/storage area in the master bedroom. Still lots of scraping being done on the outside walls, and late on Friday afternoon Dan finally arranged with a dump truck crew to remove our hugour huge pile of escombro (building debris) in the street beside the house.
Still no action
from the local water commission, although we were able to finalize
with the arquitecto that the sewage line will run to the east
to the main existing line deep under Calle 11. Luis measured and
found that the drop between the bottom of our registro and the
surface of the calle is 1.4 meters, so the fact that the main line
there is 3 meters deep indicates that it is a workable plan. They
know that our crew will only be around another week, so we have hopes
of having the city crew here early next week. Grocery shopped to
fill our freezer and refrigerator again. We feel so wealthy having
many fresh fruits and veggies in the frig. Items we never afforded
so frequently in the US.